"It is proposed to defer consideration of the application at the 19 December 2012
Planning Committee, due to the receipt of an objection to the proposal from High
Speed Two (HS2) Ltd.
"They have indicated that, whilst the application site lies
outside of the safeguarded areas for the High Speed Two development, they may
have a requirement for all or part of the site, for purposes connected with the
excavation of tunnels at Old Oak Common.
"The applicants, Clean
Power Properties Ltd & Network Rail, are therefore arranging to meet with
High Speed Two to further discuss their requirements in detail but it is likely
that these discussions will not have progressed sufficiently to allow the
application to be considered on the 19 December.
"As a result, it has been
decided that consideration of the application should be deferred until 9 January
2013 (at the earliest), although the deadline for the completion of reports for
that meeting is 21 December 2012 and timescales may be unreasonably tight."